About Namtheun One

On 9 March, 2012, Phonesack Group Co.,Ltd signed a Memorandum of Understanding (MOU) with the Government of the Lao People's Democratic Republic (GoL) to develop, own, and operate the Namtheun One Hydropower Project (NT1HPP).

Subsequently, on 25 January, 2016, Namtheun One Power Company Limited (NT1PC) was officially established. Later that year, on 14 June, 2016, the company signed a Concession Agreement (CA) with the Government of Laos to generate and sell electricity for a period of 27 years, starting from the project's Commercial Operation Date (COD).

27Years

Concession Period

Starting from June 14, 2016

2012Year

MOU Signed

March 9, 2012

2016Year

Company Established

January 25, 2016

About Namtheun One Project

The Project is located on the Nam Kading River in Bolikhamxay Province, approximately 33 km upstream of its confluence with the Mekong, and 220 km from Vientiane, central Laos.

The Nam Theun River is one of the major tributaries of the Mekong River in Lao PDR, with a catchment area of 13,856 km2 at the dam site. The Nam Theun is formed by several tributaries draining south-westwards from the Annamites to the Nakai Plateau.

The NT1 Project is the last power project in the Nam Theun – Nam Kading Hydropower Cascade.

Power Purchase Agreement

On 23 September, 2017, NT1PC signed and entered into the Power Purchase Agreement with the Electricity Generating Authority of Thailand (EGAT) and the Électricité du Laos (EDL) – these agreements are also referred to as the EGAT PPA and the EDL PPA respectively.

The total installed capacity, with 3 generating units under 2 PPAs, is 650 MW, of which 2×260 MW will be supplied to EGAT and 130 MW to EDL for the duration of 27 years commencing from the Commercial Operation Date (COD) scheduled in August 2022.

Signing ceremony

Loan partners powering NT1PC

The Namtheun One project is backed by leading Thai financial institutions delivering structured debt solutions for regional infrastructure growth.

  • USD 1.335 BProject development budget

    Total investment deployed for Namtheun One.

  • 30 %Equity contribution

    Shareholder capital supporting build-out.

  • 70 %Loan financing

    Arranged through Thai banking partners.

Project construction

Construction of the Namtheun One Hydropower Project officially began on 14 June 2016. The Roller-Compacted Concrete dam rises from an elevation of 297 meters above sea level, spanning 171 meters across the gorge and soaring 177 meters high, positioning NT1HPP as one of Southeast Asia's tallest RCC dam structures.

The construction program was structured across specialist contracts, combining large-scale civil works with precision electromechanical systems and regional transmission capabilities.

  • Dam height177 m
  • Dam crest length771 m
  • RCC concrete volume≈4 M m³
  • Crest elevation297 m ASL

Major work packages

Specialist contractors delivered each scope to global hydropower standards, ensuring resilient operations from reservoir through to grid.

Civil works

Dam, water intakes, powerhouse, and headrace tunnel, initially undertaken by the Joint Venture (JV) of Italian-Thai Development Public Company Limited (Thailand), Cooperativa Muratori e Cementisti di Ravenna (Italy), and Song Da Corporation (Vietnam), before being transferred to Sinohydro Power Company (China).

Electrical & mechanical

Power station equipment and communication systems engineered by ANDRITZ Hydro (Austria).

Transmission line

High-voltage evacuation infrastructure constructed by China Gezhouba Group (China).

Owner Engineer

Contractor information to be updated.

Main Construction Contractor

Contractor information to be updated.

Operation Contractor

Contractor information to be updated.

Social And Environment

A total of 335 households from 7 villages affected by the Namtheun One Hydropower Project reservoir area were resettled in the newly developed Huayhoy Village, located in Viengthong District, Bolikhamxay Province, approximately 12 kilometers from Namyang Village, the nearest township.

Construction of the Huayhoy resettlement area began in early December 2018 and was completed in April 2020. The resettlement site was equipped with essential infrastructure and public facilities, including:

  • A paved rubber road
  • A piped water supply system
  • A 22 kV electricity grid
  • An elementary and high school
  • A health center
  • A Buddhist temple
  • A village administrative office
  • A market
  • A transportation terminal

Sustainable Coexistence

At Namtheun One Power Company Limited (NT1PC), we are committed to ensuring construction safety, environmental protection, and community well-being. Infrastructure in and around the project area was developed with a strong focus on sustainability, aiming to support harmonious and long-term coexistence between the project and the surrounding communities.

Our Journey

9 Mar

2012

MOU to develop, own, and operate the Namtheun One Hydropower Project (NT1HPP)

25 Jan

2016

Namtheun One Power Company Limited (NT1PC) was officially established

14 Jun

2016

CONCESSION AGREEMENT (CA)

14 Jun

2016

Namtheun One Hydropower Project (NT1HPP) officially began construction

4 Sep

2017

Officially established as a shareholding company

23 Sep

2017

POWER PURCHASE AGREEMENT WITH THE ELECTRICITY GENERATING AUTHORITY OF THAILAND (EGAT)

POWER PURCHASE AGREEMENT WITH THE ELECTRICITE DU LAOS (EDL)

12 Aug

2022

COMMERCIAL OPERATION DATE (COD)